The Government has provided the Nepali Army with an extended three-year timeline to finalize the Kathmandu Terai fast track expressway project.

Completion of this road, seen as a symbol of national pride, is expected by April 3, 2030. This is the third extension granted to the army, which has been overseeing this significant project since construction commenced in May 2017.

Progress on the 70.977 km highway, which connects Khokana in Lalitpur to Nijgadh in Bara, shows that road construction is currently 50 percent complete, with 51.47 percent of funds utilized as of mid-September.

Cost increases:

Initially estimated at nearly Rs 175 billion, the project’s cost has now surged to Rs 211.93 billion, with approximately Rs 94.22 billion spent on ongoing work.

Tunnels:

The expressway consists of seven twin tunnels, amounting to a total length of 11.2 km. Both tubes of the Dhedre and Lendanda tunnels are completed, along with one of the tubes of the 3.486-kilometer long Mahadevtar tunnel, the longest on the route. Construction is still underway for the Devichaur, Sisautar, Chandram Bhir, and Mauri Bhir twin tunnels.

Bridges:

Out of the 89 elevated bridges needed for the expressway, contracts have been awarded for 85; the foundation is complete for 57, while sub-structure work is done for 38, and super-structure work is completed for 16.

Khokana land disputes and package delays: Although work is making headway on 12 packages, socio-cultural and administrative challenges have impeded overall progress.

The 6.5 km Khokana-Bungamati stretch (package 11), which serves as the entry point for the expressway, has stalled entirely due to local disputes regarding compensation, land ownership (Guthi), and cultural issues.

Additionally, delays were noted due to the contractor’s slow progress on certain aspects, particularly those that are less than 10 percent complete, prompting the government to extend the project timeline.

This multi-lane expressway will significantly reduce the travel distance between Kathmandu and the Terai region, offering an alternate route that remains accessible throughout the year, even amid monsoon